1X330MW火力发电厂主厂房吊装施工方案(英文).doc
《1X330MW火力发电厂主厂房吊装施工方案(英文).doc》由会员分享,可在线阅读,更多相关《1X330MW火力发电厂主厂房吊装施工方案(英文).doc(16页珍藏版)》请在第壹文秘上搜索。
1、I、 0相关图纸: Relevant Drawing: 主厂房钢结构安装图F312S;Steel Structure Erection Drawing of Main Building F312S 工程概况: Project Overview: 越南汪秘热电厂期扩建1330MW工程,位于汪秘原厂一侧,主厂房钢结构布置在AC排及18轴上,包括汽机房和煤仓间,汽机房吊装高度30米,煤仓间吊装高度47米。Uongbi Power Plant Extension Project No.2 (1X330MW) is at one side of the old plant. Steel structur
2、e is laid out at A-C axis and 1-8 axis of main building, covering turbine house and coal bunker bay. Lifting height of turbine house and coal bunker bay is 30m and 47m respectively. 0.000m标高为绝对标高9.000m。The elevation of0.000m equals to absolute elevation of 9.000m. 主厂房上部结构为全钢结构,节点连接采用焊接和大六角头高强螺栓连接。Su
3、perstructure of main building is steel structure. Nodes are connected together through welding and by hexagonal head high-strength bolts. 高强螺栓连接的摩擦面的摩擦系数:Q345B钢不小于0.5,Q235B钢不小于0.45。The friction coefficient between friction surface of high strength bolt connection shall be: no less than 0.5 for Q345B
4、 steel, no less than 0.45 for Q235B steel. 焊接材料:当焊接Q235钢时,手工焊采用E43型焊条;当焊接Q345钢时,手工焊采用E50型焊条。Welding material:Electrode for manual welding: E43 for Q235B steel, E50 for Q345B steel. 资源配置:Resource allocation: 人力资源计划一览表 NO:1Manpower Plan Schedule No:1 序 号No. 专业工种Type of work 人 数Quantity 工作内容Work 备 注Rem
5、ark 工程负责人Project director 施工组织及技术Construction organization and technology 测量工Surveyor 安装测量Survey for installation 起重工Hoister 装卸及吊装Handling and lifting 架子工Scaffolder 悬挂及平台绑扎Hanging and platform colligation 铆工Riveter 钢结构安装Steel structure erection 电焊工Electric welder 结构焊接Structural welding 吊车司机Crane dri