1X330火力发电站烟囱钢内筒施工方案(英文).doc
《1X330火力发电站烟囱钢内筒施工方案(英文).doc》由会员分享,可在线阅读,更多相关《1X330火力发电站烟囱钢内筒施工方案(英文).doc(11页珍藏版)》请在第壹文秘上搜索。
1、3.5 Construction Statements for the Steel Liners Erection3.5.1 Preparation at the construction site: The embedded items will be installed along with the rising construction platform, complying severely with the requirements of the drawing (see the drawing).3.5.1.1 After the steel formworks have been
2、 promoted, the platform will be applied to carry on the installation of elevator bearers and wires, hanging the steel wires for elevating circular platform, conducting the reinforcement of pulleys through the application of the elevator in the center, and installing of limit device and suspension lo
3、ops and so forth.3.5.1.2 In prior to the removal of promote platform, the 193m platform will be installed through the application of the jumpform of construction platform. After that, a 2t winch will be lifted to the platform in a appropriate distance of 3-4m to the elevator as the fixing position.
4、The 193m platform will also be utilized to install the 180m platform. And similarly it comes to the 140m one.3.5.1.3 After the promote platform removed, the distribution of cables will be conducted by the utilization of human-and-cargo elevator and cage, as well as installing, fixing and debugging f
5、or the winch. Meanwhile carry on the installation and welding of suspension points, and steel wire hanging at the 140m platform.3.5.1.4 Before the steel liners have been hoisted, a railway rolling chute will be laid in the midst of the preformed hole at the bottom of chimney stack, on which a manpow
6、ered vechicle was installed to take the steel liners in place and carry out the upset transportation from the storage yard to the erection position.3.5.1.5 The winch on the promote platform will be employed to fix the welder, winch, and the side basket as the vertical tranporting tools for platform
7、and hydraulic lifting equipments. And in ahead of lowing-down, the installation and welding of lateral bearer, bearers of suspension points and elevator, and guide pulleys on the top must be completed and in preparation.3.5.1.6 The leveling, setting out and embedded items of the pedestal of steel li
8、ner should be examined and kept with records to prepare for the febrication and installation.3.5.1.7 Preparation for hydraulic lifting equipment: it must be tested and in preparation. There will be one 5t two-tube winch, one 5t winch, one 2t winch, two 3t winches installed and in preparation. The hu