某塔装置工程脚手架搭设施工方案(英汉互译).doc
-
资源ID:948633
资源大小:133.44KB
全文页数:11页
- 资源格式: DOC
下载积分:10金币
友情提示
2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。
|
某塔装置工程脚手架搭设施工方案(英汉互译).doc
目 录Content1工程概况General12 施工依据References13施工程序Construction Procedures14施工技术要求Construction Technical Requirements25脚手架计算书Scaffolding Calculation76 HSE措施HSE Measures 91 工程概况 General 此方案用于-装置C4450、C3170、C3140、R4420、V2704、V3090、V3091、V3100、V3120、V3130、V3172脚手架搭设,脚手架用来进行平台爬梯安装工作。This method statement is prepared for the scaffolding erection for the platform & ladder installation of C4450、C3170、C3140、R4420、V2704、V3090、V3091、V3100、V3120、V3130、V3172 in.2 编制依据 References:1) 扣件式钢管脚手架搭设要求与设计计算JGJ 130-2001Erection Requirements and Design Calculation for the Steel Tubular Scaffold with Fastener JGJ 130-20012) 石油化工企业施工安全技术规程SH3505-1999Safety Technical Regulations for Petrochemical Construction SH3505-19993 施工程序 Construction Procedures施工准备材料准备机具就位N人员体检、培训Y接受架设委托 架 设N检查验收、挂合格牌Y交 付 使 用架 设 拆 除Construction PreparationTools & Equipments in PlaceNMaterial PreparationPhysical Examination & TrainingY Accept Erection EntrustingErectionInspection & Acceptance; Put on Qualification TagNYHand overScaffolding Dismantling4 施工技术要求 Construction Technical Requirements 4.1 地面处理 Ground Preparation 1) 架设前放置立杆底座板,立杆插放在底座板上,增大立杆的受力面积,增强架设的稳定性。Before erection, put the jack base under the rickers to increase the force area of rickers and strengthen the erection stability. 2) 架设用材料选用须符合下列要求:The scaffolding materials should comply with the following requirements: a) 架杆选用48mm,壁厚3.5mm的钢制管道,材质符合GB7008-79对Q-235A钢的要求。Use the steel tubes 48mm with 3.5mm thick wall as the scaffold poles. The materials should be in accordance with the requirements to steel Q-235A by GB7008-79. b) 扣件选用型号为KT-33-8的可锻铸铁,扣件紧固用螺栓选用材质为Q-235A钢制作。Use the mollealle iron KT-33-8 to be the fasteners. Bolts to fix fasteners should be fabricated by steel Q-235A.c) 跳板选用材质为Q-235A钢制作,厚度不低于2mm。Use steel Q-235A to fabricate the planks, with thickness 2mm or more.4.2 脚手架搭设型式及设备平台安装顺序Scaffolding Erection Type and Installation Sequence of Platform of Equipments1) 采用双排扣件式井字脚手架。The scaffolding shall be double-row “#”-shape scaffolding with fasteners.2) 设备平台、附塔管线安装顺序:脚手架搭设到每层平台处后(离设备平台约1.2米),安装设备平台及与下层设备连接直梯;设备平台安装完毕后,继续往上搭设脚手架,安装设备平台和爬梯。(见附图1)。 Installation sequence of equipment platform & pipelines: After the scaffolding is erected on each floor of platform (about 1.2m away from the equipment platform), install the ladders connecting the platform with the equipment at the lower level. After the completion of equipment platform installation, continue to erect scaffolding above and install the equipment platforms & ladder. (See the details in the attachment figure 1)3) 搭设脚手架时避开设备爬梯位置。Avoid the positions of equipment ladders when erecting scaffolding.4.3 双排扣件式井字脚手架搭设: Erection of Double Row “#”-Shape Scaffolding with Fasteners1) C3070塔高40.35米,直径1.5米,需要安装层8个平台和7个直爬梯(安装位置见下表),搭设5m×5m的双排井字脚手架。The column C3070 is 40.35m high, its diameter is 1.5m, and 8 platforms & 7 ladders are to be installed (installation locations see the below table), so double row “#”-shape scaffolding 5m×5m shall be erected.Platform&Ladder安装标高mmInstallation Elevation mm安装角度Installation Angle(0°为正北)(0°is True North)宽度Width mm长度Length mmPlatform1EL:4300135°320°1200Platform2EL:652790°180°900Platform3EL:10500190°245°1200Platform4EL:16000230°210°1200Platform5EL:23815200°320°1200Platform6EL:3150090°210°230°350°1200Platform7EL:37950190°330°1200Platform8EL:40250around550Ladder1EL:05470335°5470Ladder2EL:430010500180°6200Ladder3EL:1050016000220°5500Ladder4EL:1600023815335°7815Ladder5EL:2381531500220°7685Ladder6EL:3150037950330°6450Ladder7EL:3795040250210°23002) 搭设时,以双排架的形式搭设,以保证架设的稳定性,且里层架杆必须距塔壁有一定的作业距离。Try to erect in double rows to ensure the stability of scaffolding. The inside scaffold poles must keep a certain distance from the tower shell. 3) 所搭成的架设须整齐规范:立杆、横杆均须均匀布置,立杆在一条垂直线上,横杆在同一水平面上,扫地杆应沿纵向、横向连续搭设且距地面200mm。立杆采用双立杆,立杆纵距小于等于1.5米,横距不大于1.3米;大横杆步距不大于1.8米。The erected scaffolding must be in order and standard: The rickers and cross rods should be arranged uniformlyrickers should be in the same vertical line and cross rods should be in the same horizontal plane. Erect the bottom horizontal tubes continuously both longitudinally and transversely, 200mm above the ground. Use double-ricker,The longitudinal space between rickers should be 1.5m or less, transverse space should be 1.3m or less; the